These really show how things are shaping up. Within a week or so all of the walls for the cisterns, pool etc will be complete. Then they will start on the decking for the first floor slab.
You can see from the photos taken 8-12-09, they have the floor of the storage/cistern level poured, and the foundation walls and floor slab of the pool. They have the cistern walls formed and should be pouring this week. They are also starting to form up the pool walls. Those curved walls are not easy to build.